32. Temporary Service

32.1  Customers requiring temporary Electric Service may be required by the PUD to pay all costs incurred by the PUD for installation and removal of facilities prior to Electric Service being provided. The Customer will be billed for Energy consumed under the applicable Rate Schedule. If requested by a Customer or contractor, the PUD may provide an unmetered temporary Electrical Service from an existing service pedestal or pad mount transformer according to the “Premium Temporary Service Agreement” and billed at Rate Schedule 90 – Miscellaneous Charges and Fees.

32.2  Temporary Electric Service shall not exceed a twelve (12) month period, unless special conditions approved by the PUD warrant an extension of time.