Effective for all bills rendered after April 1, 2026

Applicability

To all Customers who access the PUD's transmission and distribution facilities in order to transfer or wheel power across the PUD's power grid to or from an interconnected system.

Character of Service

60 hertz alternating current at such phases and voltage as the PUD may have available.

Monthly Rate

Demand Charge: $4.34 per kW

Demand Billing Determinant: Billing Demand shall be the highest measured demand in the previous 12 months. (60-minute fixed intervals)

Special Conditions

The Customer is responsible for interconnection and line extension costs pursuant to the General Terms, Conditions, Rules, and Regulations for Electric Service. A separate contract may be required.

Other Charges & Conditions

All other charges and conditions shall be pursuant to the General Terms, Conditions, Rules, and Regulations for Electric Service.